VI-PM-2412 · Consultant · Executing
City Housing & Area Development AuthorityDevelopment authorityPimpri cluster, MaharashtraPM Neha Gokhale · Finance Kiran Joshi
Contract 1 Dec 2024 – 30 Nov 2028 · 30 days from monthly fee invoice · retention 0%
Expected profit at completion, what borrowing costs it, and how that changes if payments slip. Realised, forecast and illustrative amounts are kept apart.
Profit bridge — financing lens
= gross profit to date ₹2.14 Cr + remaining work ₹4.45 Cr × planned 22% margin
Opportunity lens Alternative lens
Return forgone at 12% on amounts collected after their due dates: ₹0 to date + ₹14,913 forecast. Profit on this lens: ₹3.12 Cr (22.0%). It replaces — never adds to — the borrowing view.
The baseline margin already includes direct costs (materials, subcontract, site payroll, equipment). It excludes financing, head-office overheads and company term-loan interest, so the deductions above are not double counted. Retention is timing, not cost.
Profit after financing if collections slip further
| Further delay | Borrowing interest | Margin after | Opportunity cost | Margin after |
|---|---|---|---|---|
| +30 days | ₹0 | 22.00% | ₹63,912 | 21.94% |
| +60 days | ₹0 | 22.00% | ₹1.3 L | 21.90% |
| +90 days | ₹0 | 22.00% | ₹1.9 L | 21.85% |
Borrowing attributable to this project
None — no borrowing is earmarked against this project's bills, so its delays cost no interest (only the opportunity lens applies).
No contractual or verified legal basis for late-payment interest is recorded for this contract, so none is assumed.
Illustrative losses — editable assumptions Illustrative
Expected collections vs this project's payments, to 31 Mar 2027 (FY end) — in ₹1.94 Cr, out ₹0.
Nothing blocking collections.
Every bill for this contract — contractual due dates and our estimated collection dates side by side.
| Bill | Stage | Work value | Outstanding | Collection |
|---|---|---|---|---|
| Fee invoices 1–21Settled bills (history roll-up) | Collected | ₹9.10 Cr | — | ₹9.10 Cr by 3 Sep |
| INV-22Monthly PMC fee — August | Submitted | ₹32.4 L | ₹32.4 L | 19 Oct est. |
| INV-23Monthly PMC fee — September | Eligible to bill | ₹32.4 L | ₹32.4 L | 17 Nov est. |
| Oct 2026 workPlanned bill for Oct 2026 work | Planned | ₹32.4 L | — | 20 Dec est. |
| Nov 2026 workPlanned bill for Nov 2026 work | Planned | ₹32.4 L | — | 19 Jan est. |
| Dec 2026 workPlanned bill for Dec 2026 work | Planned | ₹32.4 L | — | 19 Feb est. |
| Jan 2027 workPlanned bill for Jan 2027 work | Planned | ₹32.4 L | — | 22 Mar est. |
| Feb 2027 workPlanned bill for Feb 2027 work | Planned | ₹32.4 L | — | 19 Apr est. |
| Mar 2027 workPlanned bill for Mar 2027 work | Planned | ₹32.4 L | — | 20 May est. |
1 of 3 complete
Towers A–F structure
15 Jul · 15d late
Done
Towers G–M structure
plan 31 Mar
In progress
Allotment of first 1,600 homes
plan 30 Jun
Upcoming
₹0 due to 31 Mar 2027 (FY end) on this project