Cash available today
₹35.05 Cr
+ ₹6.20 Cr margin money under bank-guarantee lien — not available.
₹10.40 Cr to Narmada Transformers Ltd. (6 Nov) and ₹3.60 Cr payroll (7 Nov) fall due before Deccan Metro's ₹14.63 Cr (RA-17, est. 20 Nov) arrives.
Daily closing balance, company-wide (cash is pooled). Collections are dated by estimated receipt, payments by due date. Disputed bills are excluded.
₹142.62 Cr earned but not in the bank — each rupee counted once.
Weekly · to 31 Mar 2027 (FY end)
In ₹167.13 Cr · Out ₹186.52 Cr
Borrowing interest on the lines that late collections are meant to repay. Opportunity cost and illustrative losses are separate lenses, never added to it.
Observations generated from the records — cash and cost of delay, ranked by severity and amount.
₹10.40 Cr due to Narmada Transformers Ltd. 59 days before Vidarbha Power pays
Transformer Supply: lot 2 transformers — letter-of-credit maturity due 6 Nov; the receipt meant to fund it (₹11.43 Cr) is expected 4 Jan. Fixed — cannot be deferred.
ROB at LC-112 Final bill: approved, unpaid 94 days past due
₹9.88 Cr — Approved but unpaid — budget re-appropriation pending. Next: Meet Deputy FA & CAO; request payment from supplementary grant.
Smart City ICCC M3: approved, unpaid 73 days past due
₹4.12 Cr — Balance withheld until 140 cameras pass the site acceptance test. Next: Fix last-mile links; re-test with SPV on 15 Oct.
Transformer Supply falls below the 8.0% target margin if collections slip 23 more days
9.0% before financing → 8.1% after forecast borrowing interest. Lens: financing cost.
₹12.70 Cr of completed work uncertified for 26 days
Transformer Supply: Utility's inspection wing backlog — receipt certificate pending.
Bill discounting — ROB final bill matures 42 days after the bill is expected
If the collection (est. 25 Nov) slips past 6 Jan, ₹7.90 Cr must be repaid from own funds.
SH-72 Package II RA-11: approved, unpaid 28 days past due
₹5.83 Cr — Fund release awaited from the state budget (Q3 tranche). Next: Escalate to Chief Accounts Officer; request release from the Q3 tranche.
The distinct numbers behind the portfolio — none of them double-counted.
Contract value (incl. approved variations, excl. GST)
₹945.00 Cr