Cash available today
₹31.55 Cr
+ ₹6.20 Cr margin money under bank-guarantee lien — not available.
₹10.40 Cr to Narmada Transformers Ltd. (6 Nov) and ₹3.60 Cr payroll (7 Nov) fall due before Deccan Metro's ₹14.63 Cr (RA-17, est. 20 Nov) arrives.
Daily closing balance, company-wide (cash is pooled). Collections are dated by estimated receipt, payments by due date. Disputed bills are excluded.
₹142.62 Cr earned but not in the bank — each rupee counted once.
Weekly · to 31 Mar 2027 (FY end)
In ₹170.93 Cr · Out ₹181.11 Cr
Observations generated from the records — ranked by severity and amount.
₹10.40 Cr due to Narmada Transformers Ltd. 59 days before Vidarbha Power pays
Transformer Supply: lot 2 transformers — letter-of-credit maturity due 6 Nov; the receipt meant to fund it (₹11.43 Cr) is expected 4 Jan. Fixed — cannot be deferred.
ROB at LC-112 Final bill: approved, unpaid 94 days past due
₹9.88 Cr — Approved but unpaid — budget re-appropriation pending. Next: Meet Deputy FA & CAO; request payment from supplementary grant.
Smart City ICCC M3: approved, unpaid 73 days past due
₹4.12 Cr — Balance withheld until 140 cameras pass the site acceptance test. Next: Fix last-mile links; re-test with SPV on 15 Oct.
₹12.70 Cr of completed work uncertified for 26 days
Transformer Supply: Utility's inspection wing backlog — receipt certificate pending.
₹10.48 Cr due to Narmada Transformers Ltd. 28 days before Vidarbha Power pays
Transformer Supply: lot 3 transformers — letter-of-credit maturity due 4 Feb; the receipt meant to fund it (₹11.52 Cr) is expected 4 Mar. Fixed — cannot be deferred.
SH-72 Package II RA-11: approved, unpaid 28 days past due
₹5.83 Cr — Fund release awaited from the state budget (Q3 tranche). Next: Escalate to Chief Accounts Officer; request release from the Q3 tranche.
₹3.25 Cr disputed on District Hospital (300 beds)
Client's consultant classifies the strata as 'soft rock' rather than 'hard rock', cutting the rate by ~60%. Excluded from the forecast until resolved.
The distinct numbers behind the portfolio — none of them double-counted.
Contract value (incl. approved variations, excl. GST)
₹945.00 Cr